JEROMESVILLE (7/30/21)--We're excited to see the continued work on our new preK-12 campus!
In these photos, you can see the progress on the elementary side of the building with the steel structure for both floors in place. In addition, the steel roof decking is being installed.
The elementary gym's concrete block walls are complete, two of which are double walls, and roof trusses installed.
The cement has been poured for the 7th-12th wing of the building and the offices. The steel structure for those areas will be constructed once all the elementary-wing steel is erected.
At the field house, the brick veneer on the outside is being finished up and the metal roofing is being installed.
On the inside of the structure, the masonry walls are being painted. The mechanical, electrical, and plumbing lines are being roughed in. Framing for the different areas is also being erected.
The fencing has been installed around the track at the stadium.