May Video Update of New Campus

JEROMESVILLE (5/24/21)--In the academic wing of the new PreK-12 building, cement for the floors on the ground floor is beginning to be poured.

The blue vapor barrier that goes between the ground and the concrete is visible in the video.

The concrete trucks back up to the pump, unload, and then the concrete goes up through the line at the bottom of the big boom.

Work continues at the athletic complex with trusses going up on the field house. Also, further work has been completed on the softball, baseball and football fields.